RPN是什麼意思

RPN是什麼意思?請各位指教.謝謝!

[ 本帖最后由 jxcyf 于 2006-9-5 10:41 编辑 ]
我也来说两句 查看全部回复

最新回复

  • aong (2006-9-05 10:06:22)

    只知道PPM和RPN,不知道PPN。
  • Gavin333 (2006-9-05 10:59:55)

    我只知道RPN是FMEA中确定风险顺序数,怎么确定还没有搞过。
  • stefanie (2006-9-05 11:05:17)

    RPN是发生度(O),严重度(S),检测度(D)三者的乘积,按照所得的大小排序,所以称为风险顺序数(Risk Priority Number)。
  • 阳春白雪 (2006-9-05 11:11:04)

    去资料区下载一份FMEA手册。
  • jxcyf (2006-9-05 11:30:05)

    謝謝各位樓主,真是好人.
  • 林子 (2006-9-05 11:34:41)

    QUOTE:

    原帖由 stefanie 于 2006-9-5 11:05 发表
    RPN是发生度(O),严重度(S),检测度(D)三者的乘积,按照所得的大小排序,所以称为风险顺序数(Risk Priority Number)。
    绝对正确.
  • hutu00 (2006-9-05 11:36:51)

    路过,学习!向前辈学习!
  • yy1982 (2006-9-05 11:41:40)

    Risk Priority Number
  • allenxhw (2006-9-05 12:26:39)

    haha
    我发现很受激励的
    原来我也不知道
  • stone_tong2000 (2006-9-05 14:28:41)

    FMEA---RISK Priority Number
  • zcbear (2006-9-05 14:36:28)

    天天学习,好好向上!!
  • zhuxiaoyi (2006-9-05 14:45:03)

    学习中............
  • HUANGGUOZHENG (2006-9-05 15:48:53)

    我也不是很清楚, 只知道和FMEA有點關係.
  • huangyuwen29 (2006-9-05 15:59:58)

    感觉真的是很不错的哦
  • 005599 (2006-9-05 16:08:29)

    APQP management:
            1/ The process for manufacturing, checking and recording results of products has to be described with an APQP planning (attachment 1);
               2/ Product/Process feasibility Check-list (attached 2) has to be filled by the supplier;
            3/ A rating system based on the FMEA method shall give a priority for preventive actions. A pareto analysis of the risk criteria to design the preventive action plan could be required.
            4/ Control plan is defined for each operation in order to identify the checking operation.
            5/ Capability studies are used to asses whether the process or the machine could manufacture the product in serail conditions. In front of the results the suppliers has to decide what type of control plan to achieve.
               6/ APQP review are stated by M.A. for the common verification of the planning fullfilment.
  • heyinghuhui (2006-9-05 16:09:19)

    风险度指数(严重度*频度*探测度)
  • dreamsun (2006-9-17 08:38:23)

    我也在学习中,明白了。
  • cykcp (2006-9-17 08:59:45)

    RPN是发生度(O),严重度(S),检测度(D)三者的乘积,按照所得的大小排序,所以称为风险顺序数(Risk Priority Number)。
    再详细点说:我们公司如果RPN超过56就要进行预防措施分析,如果低于56,但是严重度超过9也要进行分析,严重度如果达到9的话,一旦出现问题后果很严重的说。所以一定要重点关注
  • wagbo (2006-9-17 13:11:12)

    解释的很详细呀,
  • bbozhang (2006-9-17 14:34:13)

    在德国也叫RPK